Posted on: Monday, July 5, 2004
Half of hillside work done at Castle Junction
By Mike Leidemann
Advertiser Transportation Writer
Work on the $7.8 million landslide prevention project at Castle Junction on O'ahu's windward side is about half done and should be finished by October, the company doing the work said last week.
The company needs about 30 more full work days to complete the hauling portion of the work, Lambert said. On a full work day, the company has been taking about 300 truckloads of dirt from the site, he said.
"We plan to start planting grass seed on some of the completed areas by next week," he said.
The state Transportation Department is funding the project to reduce the chance of rockslides along the mauka-bound lanes of Kalaniana'ole Highway near the foot of the Ko'olau Range.
The project has been slowed by numerous weather delays, but is still ahead of schedule when the rain days are accounted for, Lambert said.
Lambert said the remaining work should have a minimal impact on traffic flow in the area.
"Basically, it's getting safer and better every day. We may have the few odd temporary lane closures, but we don't anticipate any major problems as we continue. It's pretty straightforward from here on in," he said.
Reach Mike Leidemann at 525-5460 or mleidemann@honoluluadvertiser.com. • • •