'EWA BEACH
More Fort Weaver Road lane closures this week

Lane closures will continue in both directions of Fort Weaver Road today through Friday as part of the project to widen the thoroughfare from four lanes to six.

Specifically:

  • Southbound, from 8 a.m. to 2 p.m.: Left lane closures between Laulaunui Street and Old Fort Weaver Road for trenching work for the installation of electrical conduits.

  • Northbound, from 9 a.m. to 1:30 p.m.: Intermittent single-lane closures from before 'A'awa Drive to after the Honouliuli Stream Bridge for lane-striping and concrete barrier installations.

    The widening project is expected to run through mid-2009.

    Motorists are advised to use caution while driving through the area and to allow for extra travel time. Roadwork is weather-permitting.