Scheduled road work for the week beginning March 9 for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below. Road work is normally done between the hours of 8:30 a.m. and 3:30 p.m. unless otherwise noted.

'AIEA

Newtown Neighborhood – Kaahele Street Improvements, Vicinity of Komo Mai Drive to Moanalua Road. Work includes adding left turn pockets, pavement markings, and signs. Change order work has been completed. Additional extra work may be added.

(Estimated completion date: March 2008)

Reconstruction of Concrete Sidewalks – Halawa Area: Work includes: removal and reconstruction of damaged concrete sidewalk, curb and gutter areas; trimming of trees and cutting and removal of tree roots where the roots have damaged the areas; installing root barriers where required; and adjustment of utility boxes to new sidewalk grades.

(Estimated completion date: August 2008)

HONOLULU

Rehabilitation of 'Alewa Drive from Wyllie Street to Hoomaikai Street; work includes removal of existing asphalt concrete and Portland cement concrete pavements, roadway reconstruction with asphalt concrete pavement, reconstruction of existing asphalt concrete berms and concrete gutters, adjustment of utility manhole frames and covers, and installation of pavement markings, and other incidental related work.

(Estimated completion date: October 2008)

Curb ramps at Alexander Street/S. Beretania Street, Isenberg Street/S. Beretania Street, Kaheka Street/Kanunu Street, Kaheka Street/Makaloa Street, Kalauokalani Way/Makaloa Street, Punahou Street/S. King Street, S. Beretania Street/Ke'eaumoku Street/Piikoi Street, Kina'u Street/Victoria Street, S. Beretania Street/Pensacola Street/Victoria Street, S. Beretania Street/Victoria Street, S. Beretania Street/Ward Avenue, Coyne Street/University Avenue, Dole Street/East-West Road, Dole Street/University Avenue, Kahuna Lane/South King Street, University Avenue/Varsity Place, and Pawaina Street/Paumaka Place: Construct new curb ramps, sidewalks and AC transition. Install pavement striping, markings and markers, upgrade traffic signal system.

(Estimated completion date: March 2008)

Rehabilitation of Beretania Street from N. King Street to Alapa'i Street. Night work: Roadway paving from Queen Emma Street to North King Street. Adjust existing manhole frame and covers Alapa'i Street to Nu'uanu Avenue. Permanent striping work Alapa'i Street to Queen Emma Street. Traffic loop detectors Alapa'i Street to Queen Emma Street.

(Estimated completion date: April 2008)

Rehabilitation of Campbell Avenue from Kapahulu Avenue to Collins Street, Diamond Head Road from Trousseau Street to Makapuu Avenue, 4th Avenue from Waialae Avenue to Harding Avenue, Onipaa Street, Waimanu Avenue.

(Estimated completion date: April 2008)

Resurfacing of a Portion of Dillingham Boulevard, Waiakamilo Road to Middle Street. Adjusting utilities to grade; installation of pavement markings and vehicle loop detectors.

(Estimated completion date: March 2008)

Fort Street Mall and Hotel Street Sewer Replacement/Rehabilitation: Sewer line replacement and CIPP work along Hotel Street between Bethel Street and Bishop Street.

(Estimated completion date: March 2008)

Curb Ramps at Various Locations, FY 2005(3) – Hausten Street/South King Street, Kalakaua Avenue/Kapi'olani Boulevard, Ho'onanea Street/ Metcalf Street, Campus Road/Metcalf Street/University Avenue, Wai'alae Avenue/Wihelmina Rise/ 12th Avenue/Alohea Avenue, Alohea Avenue/Wela Street, Alohea Avenue/Edna Street, Mikihana Street/Mooheau Avenue, Francis Street/Upper Street, George Street/Upper Street, Hayden Street/Upper Street, Date Street/Kamoku Street/Kapi'olani Boulevard, Young Street/Kaheka Street, 14th Avenue (A)/Wai'alae Avenue, 14th Avenue (B)/Wai'alae Avenue, and Elizabeth Street/Wai'alae Avenue: Construct new curb ramps, sidewalks and AC transition. Install pavement striping, markings and markers, upgrade traffic signal system.

(Estimated completion date: March 2008)

Curb Ramps at Various Locations, FY 2004(3) – Kapi'olani Boulevard & Paani Street, Kapi'olani Boulevard & Wiliwili Street, Kapi'olani Boulevard & Pumehana Street, Kaaha Street & University Avenue, Kalakaua Avenue & Young Street, Kalakaua Avenue & South King Street, Kalakaua Avenue & Philip Street, Kalakaua Avenue & South Beretania Street, Pensacola Street & Nehoa Street, Pensacola Street & Karratti Lane, Pensacola Street & Davenport Street, Pensacola Street & Hassinger Street, Pensacola Street & Kina'u Street, Pensacola Street & South Beretania Street, Pensacola Street & Young Street, Pensacola Street & Alohi Way, Pensacola Street & Elm Street, Pensacola Street & Rycroft Street, Pensacola Street & Hoolai Street, Pensacola Street & Kaimaile Street: Construct new curb ramps, sidewalks and AC transition. Install pavement striping, markings and markers. Upgrade the traffic signal systems.

(Estimated completion date: March 2008)

Rehabilitation of Ke'eaumoku Street between Kapi'olani Boulevard to Kina'u Street; Rycroft Street from Kaheka Street to Sheridan; Sheridan Street between Kapi'olani Boulevard to South King Street; South Street from Ala Moana Boulevard to South King Street; University Avenue between Coyne Street to Hihiwai Street. Reconstruction of concrete curbs and gutters, and new bus pads. Reconstruction and resurfacing of asphalt pavements. Adjusting manhole to finish grade, installation of vehicle loop detectors, and permanent pavement markings. Paving of Ke'eaumoku Street, Rycroft Street and Sheridan Street complete; installing pavement markings and loop detectors; adjusting manhole to grade. Night paving of University Avenue complete and will be switching to daytime paving. Night paving of South Street on-going; limits to be extended up to Beretania Street.

(Estimated completion date: April 2008)

Rehabilitation of Kilauea Avenue from Hunakai Street (Mauka of H-1) to 18th Avenue. The work includes the reconstruction and resurfacing of the above street; construction of concrete bus pads; curb ramps and associated traffic signal improvements; reconstruction of curbs, gutters and driveways; installation of pavement markings, adjustment of utility covers to grade; tree trimming and root pruning.

(Estimated completion date: January 2009)

Saint Louis Heights Sewer Rehabilitation: Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and pipe bursting throughout Saint Louis Heights.

(Estimated completion date: January 2009)

Sand Island Basin Miscellaneous Sewer Rehabilitation: Continue replacement of sewer manhole frame and covers and manhole rehabilitation in various locations. Rehabilitation of the Ward Avenue sewer tunnel, Sand Island Access Road sewerline, Ala Moana Park sewerline, Moanalua sewerline and Nu'uanu sewerline are forthcoming.

(Estimated completion date: March 2008)

KAILUA

Ilimalia Loop/Mokapu Boulevard Sewer Rehabilitation: Installation of cured in place pipe (CIPP) and manhole rehabilitation within Ilimalia Loop and Mokapu Boulevard.

(Estimated completion date: June 2008)

KANE'OHE

Kawa Ditch Improvements: Naumanu Place and Nakuluai Street, Kane'ohe: Removal existing trapezoidal concrete drain channel lining and reconstruction of new concrete rectangular channel.

(Estimated completion date: March 2008)

MANOA

Rehabilitation of Streets, Unit 50 – Kalawao Place (Kalawao Street to end), Kalawao Street (Kahaloa Drive to private road), Kalehua Street (Kahaloa Drive to end), Kaloaluiki Street ( Lowrey Avenue to Kalawao Street), Kanu Street (Lowery Avenue to Loi Street), Loi Street (East Manoa Road to Woodlawn Drive), Kahawai Street (Lowrey Avenue to Huapala Street), Woodlawn Drive (Lowrey Avenue to Kahaloa Street), Lowrey Avenue (Woodlawn Drive to Kalawao Street), Kaaipu Avenue (O'ahu Avenue to end), Loomis Street (mauka end to makai end), Hiehie Street (Kaloaluiki St reetto end) and Vista Place (Lowrey Avenue to end). Work includes reconstruction and resurfacing of the above roadways; reconstruction of curbs, gutters, sidewalks and driveways; tree removal, pruning and trimming; installation of pavement markings

(Estimated completion date: November 2008)

MILILANI

Reconstruction of Concrete Sidewalks, Mililani Area, Fiscal Year 2005-2006: Work includes removal and reconstruction of damaged concrete sidewalk, curb and gutter areas; trimming of trees and cutting, removal of tree roots where the roots have damaged the areas; installing root barriers where required, and adjustment of utility boxes to new sidewalk grades, and other incidental related work.

(Estimated completion date: September 2008)

PEARL CITY

Localized Rehabilitation of Streets, Phase 2, Various Streets (Manana and Momilani): Work includes cold planing; resurfacing of asphalt concrete pavements; reconstruction of failed asphalt concrete pavement areas; adjustment of utility manhole frame and covers; installation of pavement markings; and locating existing manholes, valve boxes, monuments, etc.

(Estimated completion date: March 2008)

WAIPAHU

Waikele Road Improvements: Work includes widening of Waikele Road and addition of curb and sidewalk fronting Waipahu Intermediate School, from Farrington Highway to Waipahu Flood Control Channel; adjustment of manholes, and boxes on the roadway being widened.

(Estimated completion date: March 2008)

Localized Rehabilitation of Streets, Phase 2, Various Streets Work includes cold planing; resurfacing of asphalt concrete pavements; reconstruction of failed asphalt concrete pavement areas; adjustment of utility manhole frame and covers; installation of pavement markings; and locating existing manholes, valve boxes, monuments, etc.

(Estimated completion date: March 2008)