Kauai lane closures this week

Advertiser Staff

The State Department of Transportation has roadwork projects scheduled on Kauai this week in the following areas, weather permitting.

KAUMUALII HIGHWAY

Intermittent delays of no more than fifteen minutes may be expected in both directions on Kaumualii Highway through Frida from 8:30 a.m. to 3 p.m., daily, during construction activities at the following locations:

  • In Koloa, approximately one mile east of Maluhia Road, near Mile Post 5.7, for shoulder improvements. Completion of this project is anticipated in May 2008.

  • In Lawai, east of Piko Road Intersection, near Mile Post 9.8. Lanes in both directions will be narrowed for permit work on the highway. Completion of this project is anticipated in May 2008.

  • In Lawai, west of Koloa Road Intersection, near Mile Post 10.7. The speed limit in this area has been reduced and travel lanes narrowed and shifted temporarily, for shoulder work. Completion of this project is anticipated in May 2008.

  • In Kalaheo, between Lauoho Road and Hokua Road, near the Kalaheo Jelly Factory, for drainage and shoulder lane improvements. Completion of this project is anticipated in June 2008.

    KUHIO HIGHWAY

    Intermittent delays of no more than fifteen minutes may be expected on Kuhio Highway in both directions o through Friday from 8:30 a.m. to 3:00 p.m., daily, during construction activities at the following locations:

  • In Anahola, between Hui Road, near Mile Point 15, and Koolau Road, near Mile Point 20, for pavement resurfacing. Completion of this project is anticipated in May 2008.

  • In Anahola, near the Pili Mai Ke Kai subdivision between Anahola Road and Kukuihale Road for intersection improvements and shoulder maintenance. Completion of this project is anticipated in October 2008.

  • North of Kilauea Town at the Kolo Road intersection for intersection improvements. This project is ongoing with completion anticipated by December 2008.

    MAALO ROAD

    PAVEMENT RESURFACING

    Intermittent delays of no more than fifteen minutes may be expected in both directions through Friday from 8:30 a.m. to 3 p.m., daily, for pavement resurfacing work. Completion of this project is anticipated in June 2008.

    MOKULELE LOOP AT LIHUE AIRPORT

    PAVEMENT RESURFACING

    Single lane closures on Mokulele Loop at the Lihue Airport for pavement repairs through Friday between 7 a.m. and 5:30 p.m., daily.